Major Copper Mine in Chile


Customer Challenge
FMS Data Accuracy in Material Handling
Mining operations management was compromised due to actual material location and FMS labels in data were not corresponding.

How We Helped
In-app dumps/loads Map Developed
Dump and load events mapped to identify deviations, including location, material type, and tonnage.

The Outcome
Prevented 20,000t of ore from not being processed
The opportunity cost was set to be >USD$1 million of ore (0,2-0,4% Cu).
Corrective actions are taken to recover the ore-grade material (dumped in pit area) and the site has now a new initiative to improve dispatch procedures and FMS administration to reduce dumping errors.